Waterline Upgrade-Harris Point
Gander Bay South, Newfoundland and Labrador
Federal contribution
$105,507
Federal share33%
of $316.5K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedFeb 15, 2007
20072008
Built
Approved 8 weeks before the announcement.
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- Local Service District of Gander Bay South
- Construction start
- Oct 10, 2007(actual)
- Construction end
- Aug 22, 2008(actual)
Against the original forecast
- Construction start13 months lateforecast Sep 1, 2006
- Construction end17 months lateforecast Mar 31, 2007