Waterline Upgrade-Harris Point

Gander Bay South, Newfoundland and Labrador

completeDrinking WaterMRIF
Federal contribution
$105,507
Federal share33%

of $316.5K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedFeb 15, 2007
20072008
Built

Approved 8 weeks before the announcement.

Program
Municipal Rural Infrastructure Fund
Construction start
Oct 10, 2007(actual)
Construction end
Aug 22, 2008(actual)

Against the original forecast

  • Construction start13 months lateforecast Sep 1, 2006
  • Construction end17 months lateforecast Mar 31, 2007

Also in Gander Bay South

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 14933 in the federal list. How to read these figures.