Pumping System and Chlorination System Upgrade

Pleasantview, Newfoundland and Labrador

completeDrinking WaterMRIF
Federal contribution
$15,334
Federal share33%

of $46.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedFeb 15, 2008
20082009
Built

Approved 8 months before the announcement.

Program
Municipal Rural Infrastructure Fund
Construction start
Aug 3, 2007(actual)
Construction end
Dec 15, 2008(actual)

Against the original forecast

  • Construction start5 weeks lateforecast Jul 1, 2007
  • Construction end15 months lateforecast Sep 30, 2007