Back to projects

Reconstruction of Water Supply Dam

Portugal Cove South, Newfoundland and Labrador

completeDrinking WaterMRIF
Federal contribution
$100,388
Federal share33%

of $307.8K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 15, 2016
2010201220142016
Built

Approved 6.8 years before the announcement.

Program
Municipal Rural Infrastructure Fund
Ultimate recipient
Town of Portugal Cove South
Construction start
Jun 2, 2009(actual)
Construction end
Mar 31, 2013(actual)

Against the original forecast

  • Construction start4 weeks earlyforecast Jul 1, 2009
  • Construction end3 years lateforecast Mar 31, 2010

Also in Portugal Cove South

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 15008 in the federal list. How to read these figures.