Replacement of Bridge No.900-065

Clarksburg, Ontario

completeHighways and RoadsMRIF
Federal contribution
$494,000
Federal share33%

of $1.5M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJan 10, 2007
2007200820092010
Built

Approved 3 weeks before the announcement.

Program
Municipal Rural Infrastructure Fund
Ultimate recipient
County of Grey
Construction start
Dec 22, 2006(actual)
Construction end
Jan 7, 2010(actual)

Against the original forecast

  • Construction start12 months lateforecast Jan 1, 2006
  • Construction end10 months lateforecast Mar 15, 2009