Replacement of Mutton Bridge
Federal contribution
$127,285
Federal share33%
of $381.9K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJan 10, 2007
20072008
Built
Approved 3 weeks before the announcement.
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- Township of Cramahe
- Construction start
- Feb 1, 2007(actual)
- Construction end
- Nov 13, 2008(actual)
Against the original forecast
- Construction end13 months lateforecast Sep 30, 2007
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 15320 in the federal list. How to read these figures.