Upgrade of Water Supply Intake
Anchor Point, Newfoundland and Labrador
Federal contribution
$85,252
Federal share33%
of $255.8K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedFeb 16, 2007
20072008
Built
Approved 8 weeks before the announcement.
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- Town of Anchor Point
- Construction start
- Apr 1, 2007(actual)
- Construction end
- Feb 29, 2008(actual)
Against the original forecast
- Construction start4 weeks earlyforecast May 1, 2007
- Construction end4 months lateforecast Nov 1, 2007
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 15360 in the federal list. How to read these figures.