Water Distribution Line Improvement

Brig Bay, Newfoundland and Labrador

completeDrinking WaterMRIF
Federal contribution
$17,369
Federal share33%

of $52.1K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedNov 15, 2007
200720082009
Built

Approved 11 months before the announcement.

Program
Municipal Rural Infrastructure Fund
Construction start
Oct 7, 2008(actual)
Construction end
Dec 10, 2008(actual)

Against the original forecast

  • Construction start2.1 years lateforecast Sep 1, 2006
  • Construction end13 months lateforecast Oct 31, 2007