Uigg Community Centre Upgrades
Federal contribution
$24,263
Federal share32%
of $76.9K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedOct 10, 2006
200720082009
Built
Approved 3 months before the announcement.
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- Uigg-Kinross-Grandview Women's Institute
- Construction start
- Oct 19, 2006(actual)
- Construction end
- Apr 9, 2009(actual)
Against the original forecast
- Construction start3 months lateforecast Aug 1, 2006
- Construction end2.4 years lateforecast Oct 30, 2006
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 15472 in the federal list. How to read these figures.