Street Upgrades Various Roads
L'Anse au Clair, Newfoundland and Labrador
Federal contribution
$127,434
Federal share33%
of $382.3K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 15, 2016
2010201220142016
Built
Approved 6.9 years before the announcement.
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- Town of L'Anse Au Clair
- Construction start
- May 22, 2009(actual)
- Construction end
- Oct 30, 2012(actual)
Against the original forecast
- Construction end2.9 years lateforecast Nov 30, 2009
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 15482 in the federal list. How to read these figures.