Water System Upgrade
Bartlett's Harbour, Newfoundland and Labrador
Federal contribution
$33,752
Federal share33%
of $103.7K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedNov 15, 2007
20082009
Built
Approved 6 months before the announcement.
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- Local Service District of Bartlett's Harbour
- Construction start
- Jun 15, 2007(actual)
- Construction end
- Jan 12, 2009(actual)
Against the original forecast
- Construction start2 weeks lateforecast Jun 1, 2007
- Construction end9 months lateforecast Mar 31, 2008