Water System Upgrade

Bartlett's Harbour, Newfoundland and Labrador

completeDrinking WaterMRIF
Federal contribution
$33,752
Federal share33%

of $103.7K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedNov 15, 2007
20082009
Built

Approved 6 months before the announcement.

Program
Municipal Rural Infrastructure Fund
Construction start
Jun 15, 2007(actual)
Construction end
Jan 12, 2009(actual)

Against the original forecast

  • Construction start2 weeks lateforecast Jun 1, 2007
  • Construction end9 months lateforecast Mar 31, 2008

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 15494 in the federal list. How to read these figures.