Construction of retractable roof and pool
Saint-Narcisse-de-Beaurivage, Quebec
Federal contribution
$627,796
Federal share33%
of $1.9M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 3, 2008
20092010
Built
Approved 4 weeks before the announcement.
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- Neubois Sports Committee
- Construction start
- Oct 1, 2009(actual)
- Construction end
- Sep 15, 2010(actual)
Against the original forecast
- Construction start10 months lateforecast Nov 20, 2008
Also in Saint-Narcisse-de-Beaurivage