Montcalm Street between l'Ilménite and de l'Église streets. Waterworks and sewer upgrades.
Federal contribution
$423,930
Federal share33%
of $1.3M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 16, 2007
200720082009
Built
Approved 8 months before the announcement.
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- Town of Saint-Joseph-De-Sorel
- Construction start
- Sep 26, 2006(actual)
- Construction end
- Oct 28, 2009(actual)
Against the original forecast
- Construction end2.1 years lateforecast Sep 29, 2007
Also in Saint-Joseph-de-Sorel
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 15524 in the federal list. How to read these figures.