Miscouche Subdivision 2006
Miscouche, Prince Edward Island
Federal contribution
$109,000
Federal share33%
of $327.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedOct 10, 2006
20072008
Built
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- Community of Miscouche
- Construction start
- Nov 1, 2006(actual)
- Construction end
- Sep 8, 2008(actual)
Against the original forecast
- Construction start6 months earlyforecast May 1, 2007
- Construction end13 months lateforecast Aug 1, 2007
Also in Miscouche
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 15537 in the federal list. How to read these figures.