Sewage collection system and replacement of water mains.

Sainte-Euphémie-sur-Rivière-du-Sud, Quebec

completeWastewaterMRIF
Federal contribution
$1.4M
$1,417,263
Federal share44%

of $3.2M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 25, 2008
200920102011
Built

Approved 4 months before the announcement.

Program
Municipal Rural Infrastructure Fund
Construction start
Feb 25, 2008(actual)
Construction end
Oct 29, 2011(actual)

Against the original forecast

  • Construction start3 weeks lateforecast Feb 1, 2008
  • Construction end13 months lateforecast Sep 24, 2010