Back to projects

Revitalization of downtown Alma

Alma, Quebec

completeRecreationMRIF
Federal contribution
$2.5M
$2,518,199
Federal share33%

of $7.6M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedApr 21, 2008
2009201020112012
Built

Approved 6 weeks before the announcement.

Program
Municipal Rural Infrastructure Fund
Ultimate recipient
Village of Alma
Construction start
May 1, 2008(actual)
Construction end
Mar 31, 2012(actual)

Also in Alma