Community Centre Retrofit - Windows

Murray Harbour, Prince Edward Island

completeGreen EnergyMRIF
Federal contribution
$3,553
Federal share32%

of $11.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedOct 10, 2006
2007
Built

Approved 3 months before the announcement.

Program
Municipal Rural Infrastructure Fund
Ultimate recipient
Community of Murray Harbour
Construction start
Jan 2, 2007(actual)
Construction end
Sep 30, 2007(actual)

Against the original forecast

  • Construction start4 months lateforecast Sep 1, 2006
  • Construction end11 months lateforecast Oct 30, 2006

Also in Murray Harbour

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 15615 in the federal list. How to read these figures.