Track and Soccer

Ellerslie, Prince Edward Island

completeSportMRIF
Federal contribution
$61,283
Federal share25%

of $243.7K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedOct 10, 2006
200720082009
Built

Approved 3 months before the announcement.

Program
Municipal Rural Infrastructure Fund
Construction start
Nov 1, 2007(actual)
Construction end
Jul 30, 2009(actual)

Against the original forecast

  • Construction start16 months lateforecast Jul 14, 2006
  • Construction end2.1 years lateforecast Jun 30, 2007

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 15653 in the federal list. How to read these figures.