Back to projects

Afton Community Centre Upgrade

Afton, Prince Edward Island

completeRecreationMRIF
Federal contribution
$18,367
Federal share33%

of $55.1K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedOct 10, 2006
20072008
Built
Program
Municipal Rural Infrastructure Fund
Ultimate recipient
Community of Afton
Construction start
May 1, 2007(actual)
Construction end
Mar 30, 2008(actual)

Against the original forecast

  • Construction start6 months lateforecast Oct 30, 2006
  • Construction end9 months lateforecast Jun 30, 2007

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 15670 in the federal list. How to read these figures.