Fort Augustus Rec Centre Phase 2

Fort Augustus, Prince Edward Island

completeRecreationMRIF
Federal contribution
$34,766
Federal share33%

of $104.3K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedOct 10, 2006
2007
Built
Program
Municipal Rural Infrastructure Fund
Ultimate recipient
Fort Augustus Rec Club
Construction start
Oct 6, 2006(actual)
Construction end
Nov 30, 2007(actual)

Against the original forecast

  • Construction start3 months lateforecast Jul 3, 2006
  • Construction end5 months lateforecast Jun 30, 2007

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 15677 in the federal list. How to read these figures.