Gods Lake Narrows Community Council - Water Treatment Plant

Gods Lake Narrows, Manitoba

completeDrinking WaterMRIF
Federal contribution
$697,900
Federal share33%

of $2.1M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedDec 15, 2006
200720082009201020112012
Built

Approved 3 weeks before the announcement.

Program
Municipal Rural Infrastructure Fund
Construction start
Oct 1, 2009(actual)
Construction end
Mar 9, 2012(actual)

Against the original forecast

  • Construction start2.5 years lateforecast Apr 1, 2007
  • Construction end3.3 years lateforecast Dec 1, 2008

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 15729 in the federal list. How to read these figures.