R.M. of Rosser/R.M. of Rockwood - Lagoon

Grosse Isle, Manitoba

completeWastewaterMRIF
Federal contribution
$904,500
Federal share26%

of $3.5M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedDec 18, 2006
2007200820092010
Built

Approved 4 weeks before the announcement.

Program
Municipal Rural Infrastructure Fund
Construction start
Nov 23, 2006(actual)
Construction end
May 14, 2010(actual)

Against the original forecast

  • Construction start5 months lateforecast Jul 1, 2006
  • Construction end4 months lateforecast Dec 31, 2009