R.M. of Rosser/R.M. of Rockwood - Lagoon
Federal contribution
$904,500
Federal share26%
of $3.5M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedDec 18, 2006
2007200820092010
Built
Approved 4 weeks before the announcement.
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- Rural Municipality of Rosser
- Construction start
- Nov 23, 2006(actual)
- Construction end
- May 14, 2010(actual)
Against the original forecast
- Construction start5 months lateforecast Jul 1, 2006
- Construction end4 months lateforecast Dec 31, 2009
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 15778 in the federal list. How to read these figures.