100 Street South
Federal contribution
$2.1M
$2,056,280
Federal share33%
of $6.2M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedFeb 1, 2008
20082009201020112012
Built
Approved 4 months before the announcement.
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- Town of Morinville
- Construction start
- Jan 14, 2008(actual)
- Construction end
- Dec 9, 2011(actual)
Also in Morinville
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 15788 in the federal list. How to read these figures.