R.M. of Cartier - St. Eustache Pressure Sewer & Lagoon
Federal contribution
$385,693
Federal share22%
of $1.8M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedDec 21, 2006
200720082009201020112012
Built
Approved 4 weeks before the announcement.
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- Rural Municipality of Cartier
- Construction start
- Mar 6, 2008(actual)
- Construction end
- Jun 7, 2012(actual)
Against the original forecast
- Construction start20 months lateforecast Jul 15, 2006
- Construction end2.6 years lateforecast Oct 31, 2009
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 15792 in the federal list. How to read these figures.