Wastewater treatment in the Village Area
Federal contribution
$869,474
Federal share37%
of $2.3M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJan 29, 2007
20072008200920102011
Built
Approved 3 months before the announcement.
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- Parish of Saint-Damien
- Construction start
- Jun 1, 2008(actual)
- Construction end
- Mar 31, 2011(actual)
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 15834 in the federal list. How to read these figures.