Back to projects

Repairs to Centre sportif Odilon-Grenier

Saint-Joseph-de-Coleraine, Quebec

completeSportMRIF
Federal contribution
$77,688
Federal share22%

of $359.8K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJan 16, 2009
200920102011
Built

Approved 5 months before the announcement.

Program
Municipal Rural Infrastructure Fund
Construction start
Jan 1, 2010(actual)
Construction end
Jun 30, 2011(actual)

Against the original forecast

  • Construction start8 months earlyforecast Sep 1, 2010
  • Construction end3 months lateforecast Mar 31, 2011

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 15933 in the federal list. How to read these figures.