Marwayne & Dewberry's Renewal Plans
Federal contribution
$40,000
Federal share29%
of $135.9K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedDec 18, 2007
200820092010
Built
Approved 3 months before the announcement.
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- Village of Marwayne
- Construction start
- Jul 19, 2008(actual)
- Construction end
- Jan 16, 2010(actual)
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 15992 in the federal list. How to read these figures.