Mirror Multi Use Outdoor Recreation Facility
Federal contribution
$98,976
Federal share33%
of $296.9K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedFeb 23, 2007
20072008
Built
Approved 4 weeks before the announcement.
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- County of Lacombe
- Construction start
- May 10, 2007(actual)
- Construction end
- Oct 20, 2008(actual)
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 16059 in the federal list. How to read these figures.