Upgrades to Parc des loisirs facilities

Sainte-Marie-Salomé, Quebec

completeRecreationMRIF
Federal contribution
$29,554
Federal share33%

of $88.7K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 15, 2016
2009201120132015
Built

Approved 7.7 years before the announcement.

Program
Municipal Rural Infrastructure Fund
Construction start
Jun 16, 2008(actual)
Construction end
Aug 24, 2010(actual)

Against the original forecast

  • Construction start7 weeks lateforecast May 1, 2008
  • Construction end12 months lateforecast Sep 1, 2009

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 16085 in the federal list. How to read these figures.