Upgrades to Parc des loisirs facilities
Federal contribution
$29,554
Federal share33%
of $88.7K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 15, 2016
2009201120132015
Built
Approved 7.7 years before the announcement.
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- Parish of Sainte-Marie-Salomé
- Construction start
- Jun 16, 2008(actual)
- Construction end
- Aug 24, 2010(actual)
Against the original forecast
- Construction start7 weeks lateforecast May 1, 2008
- Construction end12 months lateforecast Sep 1, 2009
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 16085 in the federal list. How to read these figures.