Wastewater treatment infrastructures

Saint-Valentin, Quebec

completeWastewaterMRIF
Federal contribution
$864,811
Federal share34%

of $2.5M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 31, 2009
2008200920102011
Built

Approved 23 months before the announcement.

Program
Municipal Rural Infrastructure Fund
Construction start
Jun 1, 2009(actual)
Construction end
May 31, 2011(actual)

Against the original forecast

  • Construction end2 months lateforecast Mar 31, 2011

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 16088 in the federal list. How to read these figures.