Back to projects

Search for underground water and building a sanitary sewer system.

Frelighsburg, Quebec

completeDrinking WaterMRIF
Federal contribution
$2.3M
$2,291,937
Federal share38%

of $6.0M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJan 14, 2008
20082009201020112012
Built

Approved 6 months before the announcement.

Program
Municipal Rural Infrastructure Fund
Construction start
Sep 1, 2010(actual)
Construction end
Mar 31, 2012(actual)

Also in Frelighsburg

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 16089 in the federal list. How to read these figures.