Hamlet of La Crete 102 Street and 91 Avenue Improvements
Federal contribution
$150,000
Federal share10%
of $1.5M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 23, 2007
20072008
Built
Approved 8 weeks before the announcement.
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- Municipal District of Mackenzie No. 23
- Construction start
- Jun 24, 2007(actual)
- Construction end
- Nov 15, 2008(actual)