Rehabilitation of Soble Road Bridge

Maynooth, Ontario

completeHighways and RoadsMRIF
Federal contribution
$46,081
Federal share33%

of $138.2K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJan 10, 2007
200720082009
Built

Approved 3 weeks before the announcement.

Program
Municipal Rural Infrastructure Fund
Construction start
Apr 5, 2007(actual)
Construction end
May 29, 2009(actual)

Against the original forecast

  • Construction end8 months lateforecast Sep 30, 2008

Also in Maynooth

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 16256 in the federal list. How to read these figures.