Back to projects

Road Reconstruction

Richmound, Saskatchewan

completeHighways and RoadsMRIF
Federal contribution
$160,222
Federal share25%

of $640.9K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedOct 3, 2007
2008
Built

Approved 2 months before the announcement.

Program
Municipal Rural Infrastructure Fund
Construction start
Jul 24, 2007(actual)
Construction end
Oct 31, 2008(actual)

Against the original forecast

  • Construction start4 months lateforecast Apr 1, 2007
  • Construction end5 months earlyforecast Mar 31, 2009

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 16357 in the federal list. How to read these figures.