Vegreville Seed Plant Road (TWP. RD. 524)
Federal contribution
$394,479
Federal share18%
of $2.1M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedFeb 9, 2007
2007200820092010
Built
Approved 2 weeks before the announcement.
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- County of Minburn No. 27
- Construction start
- Oct 23, 2007(actual)
- Construction end
- Dec 21, 2009(actual)
Also in Minburn
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 16379 in the federal list. How to read these figures.