Back to projects

Water System Upgrade

Manor, Saskatchewan

completeDrinking WaterMRIF
Federal contribution
$110,570
Federal share25%

of $442.3K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 5, 2007
200720082009
Built

Approved 2 months before the announcement.

Program
Municipal Rural Infrastructure Fund
Ultimate recipient
Village of Manor
Construction start
Dec 20, 2006(actual)
Construction end
Mar 9, 2009(actual)

Against the original forecast

  • Construction end3 weeks earlyforecast Mar 31, 2009

Also in Manor

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 16385 in the federal list. How to read these figures.