Heavy Haul Corridor

Golden Prairie, Saskatchewan

completeHighways and RoadsMRIF
Federal contribution
$163,266
Federal share25%

of $653.1K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedOct 3, 2007
2008
Built

Approved 2 months before the announcement.

Program
Municipal Rural Infrastructure Fund
Construction start
Jul 24, 2007(actual)
Construction end
Dec 5, 2008(actual)

Against the original forecast

  • Construction start8 months earlyforecast Apr 1, 2008
  • Construction end4 months earlyforecast Mar 31, 2009

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 16446 in the federal list. How to read these figures.