Heavy Haul Corridor
Federal contribution
$163,266
Federal share25%
of $653.1K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedOct 3, 2007
2008
Built
Approved 2 months before the announcement.
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- Rural Municipality of Big Stick No. 141
- Construction start
- Jul 24, 2007(actual)
- Construction end
- Dec 5, 2008(actual)
Against the original forecast
- Construction start8 months earlyforecast Apr 1, 2008
- Construction end4 months earlyforecast Mar 31, 2009
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 16446 in the federal list. How to read these figures.