Renewal of Glennelm Road Bridge and Buttermilk Falls Road Bridge
Federal contribution
$214,067
Federal share33%
of $642.2K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJan 10, 2007
200720082009
Built
Approved 3 weeks before the announcement.
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- Town of Greater Napanee
- Construction start
- Jan 1, 2007(actual)
- Construction end
- Feb 17, 2009(actual)
Against the original forecast
- Construction start3 months earlyforecast Apr 2, 2007
- Construction end6 weeks earlyforecast Mar 31, 2009
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 16471 in the federal list. How to read these figures.