Water System Improvements

Rushoon, Newfoundland and Labrador

completeDrinking WaterMRIF
Federal contribution
$72,337
Federal share33%

of $217.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 15, 2016
2010201220142016
Built

Approved 6.7 years before the announcement.

Program
Municipal Rural Infrastructure Fund
Ultimate recipient
Town of Rushoon
Construction start
Aug 3, 2009(actual)
Construction end
Oct 9, 2013(actual)

Against the original forecast

  • Construction start7 weeks earlyforecast Sep 18, 2009
  • Construction end3.8 years lateforecast Dec 31, 2009

Also in Rushoon

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 16475 in the federal list. How to read these figures.