Water System Improvements
Rushoon, Newfoundland and Labrador
Federal contribution
$72,337
Federal share33%
of $217.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 15, 2016
2010201220142016
Built
Approved 6.7 years before the announcement.
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- Town of Rushoon
- Construction start
- Aug 3, 2009(actual)
- Construction end
- Oct 9, 2013(actual)
Against the original forecast
- Construction start7 weeks earlyforecast Sep 18, 2009
- Construction end3.8 years lateforecast Dec 31, 2009
Also in Rushoon
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 16475 in the federal list. How to read these figures.