Replacement of Huron Street and Joseph Street Bridges

Walkerton, Ontario

completeHighways and RoadsMRIF
Federal contribution
$226,666
Federal share33%

of $680.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJan 10, 2007
200720082009
Built

Approved 3 weeks before the announcement.

Program
Municipal Rural Infrastructure Fund
Ultimate recipient
Municipality of Brockton
Construction start
Dec 22, 2006(actual)
Construction end
Apr 4, 2009(actual)

Against the original forecast

  • Construction start2.1 years lateforecast Dec 1, 2004

Also in Walkerton

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 16487 in the federal list. How to read these figures.