Main Street Upgrade

Eston, Saskatchewan

completeHighways and RoadsMRIF
Federal contribution
$84,475
Federal share25%

of $337.9K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 6, 2007
200720082009
Built

Approved 2 months before the announcement.

Program
Municipal Rural Infrastructure Fund
Ultimate recipient
Town of Eston
Construction start
Dec 20, 2006(actual)
Construction end
Dec 30, 2008(actual)

Against the original forecast

  • Construction start3 months earlyforecast Apr 1, 2007
  • Construction end9 months lateforecast Mar 31, 2008

Also in Eston

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 16505 in the federal list. How to read these figures.