Water Treatment Plant Upgrade

Paradise Hill, Saskatchewan

completeDrinking WaterMRIF
Federal contribution
$250,000
Federal share19%

of $1.4M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedApr 3, 2007
20072008
Built

Approved 3 months before the announcement.

Program
Municipal Rural Infrastructure Fund
Ultimate recipient
Village of Paradise Hill
Construction start
Dec 20, 2006(actual)
Construction end
Sep 15, 2008(actual)

Against the original forecast

  • Construction end6 months earlyforecast Mar 31, 2009

Also in Paradise Hill

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 16510 in the federal list. How to read these figures.