Stabilization of South Saugeen River Bank by the Neustadt Lagoons

Neustadt, Ontario

completeWastewaterMRIF
Federal contribution
$766,736
Federal share33%

of $2.3M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJan 10, 2007
2007200820092010
Built

Approved 3 weeks before the announcement.

Program
Municipal Rural Infrastructure Fund
Ultimate recipient
Municipality of West Grey
Construction start
Apr 1, 2007(actual)
Construction end
Oct 31, 2010(actual)

Against the original forecast

  • Construction end13 months lateforecast Sep 30, 2009

Also in Neustadt

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 16513 in the federal list. How to read these figures.