Construction of Three Household Waste Depots
Federal contribution
$30,694
Federal share33%
of $92.1K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJan 10, 2007
2007200820092010
Built
Approved 3 weeks before the announcement.
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- Township of North Frontenac
- Construction start
- Feb 9, 2007(actual)
- Construction end
- Dec 22, 2009(actual)
Against the original forecast
- Construction end10 months earlyforecast Oct 31, 2010