Water Well (Hamlet of Wishart)

Wishart, Saskatchewan

completeDrinking WaterMRIF
Federal contribution
$8,885
Federal share25%

of $35.5K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 14, 2007
2008
Built

Approved 7 weeks before the announcement.

Program
Municipal Rural Infrastructure Fund
Construction start
Jul 24, 2007(actual)
Construction end
May 9, 2008(actual)

Against the original forecast

  • Construction start4 months lateforecast Apr 1, 2007
  • Construction end6 weeks lateforecast Mar 31, 2008