Wastewater treatment
Federal contribution
$3.5M
$3,519,751
Federal share48%
of $7.4M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 9, 2007
200820092010201120122013
Built
Approved 5 months before the announcement.
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- Municipality of Portneuf-Sur-Mer
- Construction start
- Jun 1, 2009(actual)
- Construction end
- Dec 16, 2012(actual)
Against the original forecast
- Construction start5 months lateforecast Jan 1, 2009
- Construction end16 months lateforecast Aug 31, 2011
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 16673 in the federal list. How to read these figures.