Replacement of Hanna Road Bridge
Federal contribution
$102,107
Federal share33%
of $306.3K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJan 10, 2007
20072008
Built
Approved 3 weeks before the announcement.
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- Township of Oliver Paipoonge
- Construction start
- Apr 1, 2007(actual)
- Construction end
- Feb 6, 2008(actual)
Against the original forecast
- Construction start4 weeks earlyforecast May 1, 2007
- Construction end3 months lateforecast Oct 31, 2007
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 16686 in the federal list. How to read these figures.