Back to projects

Water Project

Kamsack, Saskatchewan

completeDrinking WaterMRIF
Federal contribution
$125,913
Federal share25%

of $503.6K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 14, 2007
20082009201020112012
Built

Approved 7 weeks before the announcement.

Program
Municipal Rural Infrastructure Fund
Ultimate recipient
Town of Kamsack
Construction start
Jul 24, 2007(actual)
Construction end
Nov 9, 2011(actual)

Against the original forecast

  • Construction start4 months lateforecast Apr 1, 2007
  • Construction end19 months lateforecast Mar 31, 2010

Also in Kamsack

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 16729 in the federal list. How to read these figures.