Devolopment of Parc Marie-Victorin
Federal contribution
$1.6M
$1,607,314
Federal share33%
of $4.8M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 28, 2011
20092010201120122013
Built
Approved 3.1 years before the announcement.
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- Marie-Victorin Park
- Construction start
- Jul 9, 2008(actual)
- Construction end
- Mar 20, 2013(actual)
Against the original forecast
- Construction end22 months lateforecast May 31, 2011
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 16753 in the federal list. How to read these figures.