Back to projects

Truck Route

Carmichael No. 109, Saskatchewan

completeHighways and RoadsMRIF
Federal contribution
$149,538
Federal share25%

of $598.2K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 6, 2007
2007200820092010
Built

Approved 2 months before the announcement.

Program
Municipal Rural Infrastructure Fund
Construction start
Dec 20, 2006(actual)
Construction end
Dec 31, 2009(actual)

Against the original forecast

  • Construction end3 months earlyforecast Mar 31, 2010

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 16770 in the federal list. How to read these figures.