Belliveau Cove Sewer System Extension

Belliveau Cove, Nova Scotia

completeWastewaterMRIF
Federal contribution
$50,254
Federal share33%

of $150.8K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedOct 29, 2007
200820092010
Built

Approved 2 months before the announcement.

Program
Municipal Rural Infrastructure Fund
Construction start
Aug 22, 2007(actual)
Construction end
Jan 2, 2010(actual)

Against the original forecast

  • Construction start21 months lateforecast Nov 24, 2005
  • Construction end3 months earlyforecast Mar 31, 2010

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 16778 in the federal list. How to read these figures.